Sprint 11 Planning
The first priority is getting as much programming done as I can before Wednesday morning. After that, it’s all about getting the presentation done and brushing up on past coursework. So those are the sprint goals.
So the sprint backlog items are:
This is a total of 26.5 hours which must be completed before 1pm on Friday. Since I have taken 3 days off and intend to spend them working just on this, it seems feasible. At this point I haven’t got much choice!
So the sprint backlog items are:
Priority | Description | Points |
---|---|---|
800 | Mark subtasks on the project page. | .5 |
790 | ”Task created” page should return to the project page. | .5 |
780 | Add a link to the login page/project page (depending on whether or not the user is logged in) to the error page. | .5 |
770 | Turn the subtask radio buttons on the task/new task pages into a drop down list. | 2 |
760 | Change the dependency checkboxes on the task/new task pages into a drop down and a button to add more drop downs as needed. | 2 |
750 | Make the comment text box count down how many characters remain as the user types. | 2 |
740 | Add a javascript calendar picker for date fields. | 3 |
730 | Make the task list on the project page a sortable table. | 3 |
720 | Create slides for the presentation. | 3 |
710 | Study for the oral exam. | 8 |
700 | Practice presentation and demo. | 2 |
This is a total of 26.5 hours which must be completed before 1pm on Friday. Since I have taken 3 days off and intend to spend them working just on this, it seems feasible. At this point I haven’t got much choice!